Proof of the Power Company
Finally the power company has been there. Now I just need them to hook up the temporary power.
Date: 10/06/2005
Views: 338
|
A view the day before the pour.
Date: 10/06/2005
Views: 307
|
Anchor Bolts
Here are the garage anchor bolts laying on the templates.
Date: 10/06/2005
Views: 223
|
|
Wire Mesh and Vapor Barrier
All the wire mesh and vapor barrier is in place.
Date: 10/06/2005
Views: 217
|
Rebar and Anchor Bolts
Here you can see the mammoth amount of rebar I was required to have and also another set of the anchor bolts. The bar sticking out from under the form is a ground rod for the garage electrical.
Date: 10/06/2005
Views: 223
|
The Pump Truck
This is a shot of the pump truck with the flash on. This is how dark it was when they started pouring!
Date: 10/07/2005
Views: 198
|
|
The Pump Truck
This is the pump truck again, with no flash. Even darker!
Date: 10/07/2005
Views: 180
|
Pump Truck?
Honestly... I have no idea, but I think it is the pump truck.
Date: 10/07/2005
Views: 183
|
The Pump Truck
Here is the pump truck with someones headlights on it.
Date: 10/07/2005
Views: 184
|
|
1st Concrete Truck
This is the first concrete truck of the 10 that came.
Date: 10/07/2005
Views: 180
|
Concrete Truck Bellied To Pump Truck
Here the pumper truck has the boom in place and the first of 10 concrete trucks is bellied up to the hopper.
Date: 10/07/2005
Views: 184
|
Filling the Footers
Here are the guys from edge concrete filling the footers.
Date: 10/07/2005
Views: 167
|
|
Filling the Footers
Here is a closer (and still not visible) shot of them filling the footers. I tried to not use the flash as I did not want to distract them.
Date: 10/07/2005
Views: 376
|
Filling the Floor
Here the guys are getting ready to start filling the floor in.
Date: 10/07/2005
Views: 171
|
Concrete Truck and the Pump Truck
This is a nice visible shot of the pumper and the first concrete truck.
Date: 10/07/2005
Views: 169
|
|
The Crew!
Date: 10/07/2005
Views: 176
|
Huge Boom
That truck had a HUGE boom. And I was told it was a little pump. LOL!
Date: 10/07/2005
Views: 160
|
Waste not, want not!
This was the waste from the chutes on the trucks. It was quite a large pile by the time they were done.
Date: 10/07/2005
Views: 192
|
|
Filled Footer
(Snuck a couple of flashed shots in.) This is the corner footer after it was filled and before the floor was filled in.
Date: 10/07/2005
Views: 189
|
The Guys!
This was probably the best shot I got of the guys working. It was just the right amount of light. That hose was puking the concrete out.
Date: 10/07/2005
Views: 208
|
Filling the Floor
Here they are filling the floor in.
Date: 10/07/2005
Views: 172
|
|
Hose
Look at that thing puking that concrete.
Date: 10/07/2005
Views: 167
|
A Concrete Ballet
Here they are screeding the surface. They truely moved together like a ballet!
Date: 10/07/2005
Views: 305
|
Screeding
The guys in the back used the "rakes" to keep just the right amount of materials there for the 2 guys running the screed. It was pretty amazing to watch.
Date: 10/07/2005
Views: 308
|
|
Smoooooth!
I kept saying to myself, "It doesn't look very smooth." But they made it smooth!
Date: 10/07/2005
Views: 202
|
More to screed!
Still screeding. They have not filled in the far end of the floor yet.
Date: 10/07/2005
Views: 162
|
Bowl Float
Now the concrete is getting the bowl float.
Date: 10/07/2005
Views: 419
|
|
Bowl Float
More Bowl Float action.
Date: 10/07/2005
Views: 348
|
What was that? Waste Not, Want Not?
This is what happens when you are 2 yards short on your order. :( Remember that waste not pile? LOL! Seriously though, the order was 2 cubic yards short and the 10th truck had to be ordered. 92 cubic yards total!
Date: 10/07/2005
Views: 222
|
And in an instant...
There she was!
Date: 10/07/2005